Critical Path Method Example: Calculate Project Duration With 5 Tasks

For a simple project with fixed durations, sufficient resources, and finish-to-start dependencies, add up the durations on each path from start to finish. The longest path is the critical path. Its duration sets the earliest possible finish.

When two branches run in parallel, the task where they rejoin has to wait for whichever branch finishes last.

List what each task waits for

For a course registration page, confirm the scope first. The team can then build the form and write the copy in parallel. Copy review depends on the draft. Integration and launch require both the form and approved copy.

Five activities for the registration page
IDTaskPredecessorWorkdays
AConfirm scope—2
BBuild formA4
CDraft copyA2
DReview copyC1
EIntegrate and launchB and D1

Use the later finish at the join

Start the clock at zero. A finishes at the end of day 2. B ends on day 6. C and D together finish on day 5. E waits until the end of day 6 and takes one day, so the earliest finish is day 7.

Two dependency paths and their durations in a TodoNote note
Keep each duration beside its dependencies so you can recalculate when work slips.

Adding each path gives the same answer. A→B→E totals 7 workdays. A→C→D→E totals 6, leaving one workday of float on the copy branch under this schedule.

Try a delay on each branch

If B takes one extra day, E moves by one day and the project takes 8 workdays. If D alone takes an extra day, both branches reach the join at the end of day 6 and the finish stays on day 7. The copy branch has used its float.

If the same person has to build the form and draft the copy, sequence their work first and recompute. Dates, dependencies, and resource limits can all change which path drives the finish.

Use the calculation in your schedule

In TodoNote, create tasks A through E, keep predecessor and duration notes, and plan start dates around expected predecessor finishes. Recalculate at the join whenever an estimate changes before you revise the delivery date.